204 flat buyers get MahaRERA relief: Redshift Buildcon ordered to execute conveyance within 60 days
Developer’s plea to wait for completion of other buildings rejected; MahaRERA directs joint inspection within 15 days and free rectification of eligible defects within 30 days
2 मिनट पठन

Pune: A developer cannot keep flat buyers waiting indefinitely for ownership rights by citing unfinished construction elsewhere in a project. Sending out a strong message against such delays, the Maharashtra Real Estate Regulatory Authority (MahaRERA) has directed Redshift Buildcon to execute and register the conveyance deed for Buildings A and B of its Bloomville residential project within 60 days, bringing relief to 204 flat purchasers.
The order, passed by MahaRERA Member Mahesh Pathak, came on a complaint filed by Bloomville A and B Wing S.G.S. Maryadit, representing 204 flat buyers. The society had raised several grievances, including incomplete construction work, defective amenities, inadequate water supply and the developer's failure to execute the conveyance deed.
‘Other buildings cannot hold buyers hostage’
During the proceedings, Redshift Buildcon argued that the conveyance process should be postponed until the remaining buildings in the project layout were completed.
MahaRERA rejected the developer's justification, making it clear that pending construction in other buildings and disputes with landowners could not become grounds for indefinitely withholding conveyance for Buildings A and B.
The direction is significant for the 204 purchasers, as the authority has ordered the developer to complete the conveyance process within a fixed 60-day deadline rather than allowing the matter to remain pending.
Developer given 15 days for joint inspection
MahaRERA has also directed Redshift Buildcon to conduct a joint inspection of Buildings A and B along with the housing society within 15 days. The inspection must be carried out through a qualified engineer to identify structural and other defects.
The authority has further ordered that defects falling under Section 14(3) of the Real Estate (Regulation and Development) Act, 2016, must be rectified within 30 days from the inspection, without charging the society any amount.
However, this direction applies to defects covered by the statutory five-year defect liability period.
No extra cost to buyers for eligible defects
The order places a clear responsibility on the developer to address eligible defects without passing the repair costs on to homebuyers. For the 204 flat purchasers, the directions address two critical issues — securing conveyance of their buildings and obtaining repairs for defects covered under the law.
The ruling reinforces that developers cannot use delays in other parts of a larger project or disputes with landowners as an open-ended excuse to deny buyers their conveyance rights.