BUILDER’S BID TO THROW OUT 11 HOME BUYERS REJECTED! Anuj Goel in Trouble

MAHARERA ORDERS GANGA AMBER DEVELOPER TO PAY DELAY INTEREST FROM JANUARY 2025 Authority rejects promoter’s counter-cases seeking cancellation of flat bookings and permission to resell; rules that emails and meeting minutes cannot override registered possession deadlines

વિક્રાંત કુલકર્ણી
વિક્રાંત કુલકર્ણી

7 મિનિટ વાંચન

BUILDER’S BID TO THROW OUT 11 HOME BUYERS REJECTED! Anuj Goel in Trouble
MAHARERA ORDERS GANGA AMBER DEVELOPER TO PAY DELAY INTEREST FROM JANUARY 2025

PUNE : In a major setback to Shri Siddhivinayak Developers, MahaRERA has rejected the builder’s attempt to terminate the agreements of 11 homebuyers and reclaim their flats for resale, while directing it to pay interest for delaying possession of their homes. The Authority has made it clear that a builder cannot escape its contractual commitment by relying on emails, meeting minutes or an administrative extension of the project registration. It has ordered the promoter to pay delay interest from January 1, 2025, until the flats are handed over with Occupancy Certificates (OCs), besides awarding ₹20,000 in costs to each of the 11 buyers.

Ganga Amber Phase II, D Wing, in Pimpri-Chinchwad, registered under MahaRERA number P52100026055. The 45-page order disposes of a batch of 22 connected complaints — 11 filed by homebuyers against the promoter and 11 counter-complaints filed by the promoter against the same buyers.

The buyers had approached the Authority seeking possession, interest for delayed handover under Section 18 of the Real Estate (Regulation and Development) Act, 2016, and other reliefs. In its counter-offensive, the promoter sought termination of their agreements, execution of cancellation deeds within eight days, permission to resell the flats and ₹5 lakh in compensation along with ₹1 lakh towards costs.

MahaRERA rejected all 11 counter-complaints, holding that the promoter had failed to establish a valid basis to cancel the buyers’ agreements. It directed the developer to hand over the flats after receiving any legitimate balance consideration, along with the statutory delay interest.

REGISTERED POSSESSION DATE CANNOT BE REWRITTEN THROUGH EMAILS

A key issue before the Authority was whether the promoter could rely on a project-registration extension and a meeting held on September 9, 2024, to shift the possession deadline. The registered agreements for all 11 flats had promised possession by December 31, 2024. The promoter, however, relied on the meeting minutes and subsequent communications to argue that buyers had accepted an extended timeline.

The promoter contended that the buyers had been informed that possession would be delivered by June 30, 2026, and that they had consented to the extension. It further argued that the buyers had chosen to continue with their bookings after receiving an email dated December 23, 2024, offering them the option of either accepting the revised timeline or cancelling their bookings and taking a refund.

The Authority rejected this defence. It held that an extension granted to a project’s registration is an administrative decision and does not automatically alter the possession date agreed upon between the promoter and the allottee in a registered agreement for sale.

The order also makes it clear that meeting minutes or email exchanges cannot substitute a registered supplementary agreement when the contractual possession date is sought to be changed. If the promoter knew it could not meet the original deadline, it should have executed appropriate registered supplementary agreements with the buyers.

The Authority’s reasoning leaves little room for promoters to treat informal communications as a substitute for legally registered contractual changes.

COVID, CIVIL SUIT AND STOP-WORK ORDER FAIL TO SAVE BUILDER

The promoter attributed the delay to a civil suit filed by Ganga Aurum Park Co-operative Housing Society, the COVID-19 pandemic, labour-related difficulties and a stop-work order issued by the Deputy Labour Commissioner, Pune, on May 25, 2023, following the death of a 21-year-old worker at the site on September 15, 2022.

It relied on the force majeure clause in the agreements, arguing that government restrictions and delayed permissions had affected construction. It also claimed that the buyers had waived their right to delay interest by consenting to the revised project timeline.

The buyers disputed these explanations. They argued that their agreements were executed after the pandemic had begun and that COVID could not be used as a blanket excuse for the delay. They also contended that the civil suit concerned a different project, Ganga Aurum, and that the September 2024 meeting minutes were merely an unsigned email rather than a registered supplementary agreement.

The Authority found the promoter’s explanations insufficient to defeat the buyers’ statutory claim. It held that the project-registration extension did not erase the original contractual deadline and that the promoter could not rely on informal communications to establish a waiver of the buyers’ rights.

BUILDER’S DOUBLE STANDARD EXPOSED IN COUNTER-CASES

The promoter’s counter-complaints accused the buyers of defaulting on payments. Relying on Clause 14 of the agreements and Section 11(5) of RERA, the developer claimed that it had issued a 15-day notice and was entitled to terminate the agreements and recover the flats.

The outstanding amounts claimed by the promoter ranged from approximately ₹7.70 lakh to nearly ₹20 lakh across the 11 flats. It argued that buyers were required to continue making payments even if construction was delayed.

The buyers countered that the demands were premature because the promoter had not achieved the construction milestones linked to the payment schedule. They disputed the outstanding calculations, questioned the absence of separate 15-day notices and said they were willing to pay legitimate dues after reconciliation.

Some buyers also alleged discrepancies in the amounts demanded. The buyer of flat D-301, for instance, claimed that the promoter had inflated the consideration by ₹1,57,492 and failed to account for a separate parking payment of ₹3 lakh.

MahaRERA found the promoter’s position inconsistent. While blaming external circumstances for its own failure to complete the project on time, the promoter was simultaneously accusing buyers of defaulting on payments. The Authority also found that the promoter’s interpretation of Clause 14 was not supported by the clause and noted that the developer itself had failed to achieve the construction stages contemplated in the payment schedule.

It therefore rejected the promoter’s attempt to terminate the agreements on the basis of alleged payment defaults.

BUYERS’ RENT AND EMI BURDEN HIGHLIGHTED

The buyers told the Authority that they had been left paying home-loan EMIs and monthly rent while waiting for possession. Their complaints cited substantial financial burdens.

One buyer of flat D-904 stated that the monthly EMI was ₹37,651, in addition to rent of ₹33,000. The buyer of D-504 cited an EMI of ₹32,206 and rent of ₹14,000. Another buyer of D-501 stated that the monthly EMI was ₹18,538, insurance was ₹1,100 and rent was ₹20,000.

The buyers also alleged that construction had been substantially delayed and that the promoter had repeatedly pressured them to accept refunds or agree to revised timelines. The buyer of D-804 separately alleged that the booking had been cancelled on October 19, 2022, and subsequently reconfirmed at a higher consideration of ₹60,52,800, compared with the earlier figure of ₹56,42,026.

The promoter denied the allegations and accused the buyers of using the complaints to avoid paying their outstanding dues. It also sought ₹5 lakh for alleged harassment and defamation.

While MahaRERA directed payment of statutory delay interest, it did not grant separate compensation for mental agony, rent or EMI expenses. Relying on the Bombay High Court’s ruling in Neelkamal, the Authority held that interest under Section 18 itself is compensatory. It nevertheless awarded costs because the buyers had been compelled to approach the Authority to enforce their rights.

BUILDER MUST PAY INTEREST UNTIL POSSESSION WITH OC

Under the operative directions, the promoter must hand over the 11 flats after receiving any balance consideration legally payable under the respective agreements. It must pay interest on the amounts paid towards the flat consideration, at the rate prescribed under Rule 18 of the Maharashtra RERA Rules, 2017, from January 1, 2025, until actual handover of possession with the Occupancy Certificate.

The Authority has permitted the promoter to adjust the interest payable against any legitimate balance dues under the agreements. Any remaining interest amount must be paid to the respective buyers at the time of handover.

Importantly, the interest calculation will cover only the consideration paid towards the flat. Stamp duty, registration charges, taxes and other statutory payments have been excluded from the interest-bearing amount.

The promoter has also been directed to pay ₹20,000 as costs in each of the 11 buyer complaints. The Authority has not imposed a separate penalty or ordered any additional compensation.