15-Year delay, ₹63.50-cr bill: PMC turns to compulsory acquisition to break Kharadi–Shivane Road deadlock
A one-kilometre stretch in Vadgaon Sheri remains stuck over land acquisition; 24,000 sq m to be acquired under 2013 law as Pune continues to wait for a crucial east–west road link
3 મિનિટ વાંચન

A one-kilometre stretch in Vadgaon Sheri remains stuck over land acquisition; 24,000 sq m to be acquired under 2013 law as Pune continues to wait for a crucial east–west road link
Pune: A road planned nearly four decades ago is still struggling to become a continuous transport link, with the Pune Municipal Corporation (PMC) now preparing to spend ₹63.50 crore to acquire land for a missing one-kilometre stretch of the Kharadi–Shivane road. After over 15 years of delay over land acquisition in Vadgaon Sheri, the civic administration has turned to compulsory acquisition to break the deadlock.
The proposed acquisition covers around 24,000 square metres of land along the Mula-Mutha riverbank, affecting landowners in Survey Nos. 5, 55, 56 and 59. The PMC has forwarded proposals to the government, seeking to initiate the process under the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013.
The financial burden is substantial. Based on the 2026–27 ready reckoner rate of ₹26,460 per square metre, the land acquisition is estimated to cost the civic body ₹63.50 crore. The amount highlights the mounting financial implications of the prolonged delay in securing land for a critical road project. The Kharadi–Shivane road was incorporated into the PMC's 1987 Development Plan as a 17.21-km riverside corridor intended to connect eastern and western Pune. However, the project remains fragmented, with several stretches yet to be completed. Of the crucial 11.21-km stretch between Sangamwadi and Kharadi, around 9.70 km has been completed, while 9.40 km has been opened to traffic. The missing section at Vadgaon Sheri has prevented the road from functioning as a continuous corridor. The civic administration has submitted two separate acquisition proposals to the Collector's land acquisition branch—one for Survey No. 5 and another covering Survey Nos. 55, 56 and 59. The process will require approvals from the Standing Committee and the PMC general body, followed by the prescribed statutory steps.
The land acquisition hurdle is not confined to Vadgaon Sheri. The Warje–Mhatre Bridge stretch also remains incomplete. The PMC is pursuing acquisition for approximately 2.5 km between Jawalkar Garden and Mahalaxmi Lawns in Karvenagar, with officials indicating that several parcels could be taken over within the next one-and-a-half to two months. Further acquisition is also planned between Rajaram Bridge and Mhatre Bridge. Rajesh Bankar, Chief Engineer, Road Department, PMC, said the proposal for compulsory acquisition of the pending land in Vadgaon Sheri had been sent to the Collector's office. For residents and commuters, the latest move offers a possible breakthrough—but also underlines how a road conceived in 1987 has remained incomplete despite years of planning. The ₹63.50-crore acquisition proposal may finally move the project forward, but the actual completion of the corridor will depend on how swiftly the statutory acquisition process is carried out.